Document Revision date versus Upload date for version hierarchy

Request that Mercury can read and sort revision dates to determine version hierarchy rather than be based on upload date.

Ex: 2 RFI’s that update the same drawing sheet are answered 2 days apart. The first RFI’s drawings are dated 11/20, but due to the second RFI actually having been submitted first its drawings are dated 11/18. If we base version hierarchy off the upload date, the later RFI will be in he wrong position.

Recommend reviewing the “info” page for a drawing in Procore. This page allows you to edit all the attributes for the document (name, discipline, number, etc) as well as modifying attributes of the versions and the ability to move versions around to ensure they are ordered correctly.

Please authenticate to join the conversation.

Upvoters
Status

In Review

Board

💡 Feature Request

Date

3 months ago

Author

Zach Hughes

Subscribe to post

Get notified by email when there are changes.